CAPM förkortningar

The exercise was created 2022-08-03 by josefinflach. Question count: 26.




Select questions (26)

Normally, all words in an exercise is used when performing the test and playing the games. You can choose to include only a subset of the words. This setting affects both the regular test, the games, and the printable tests.

All None

  • WBS work breakdown structure
  • PMO project management office
  • OPAs organizational process assets
  • EEFs enterprise environmental factors
  • PMIS project management information system
  • PV planned value
  • EV earned value
  • AC actual cost
  • BAC budget at completion
  • EAC estimate at completion
  • ETC estimate to completion
  • VAC variance at completion
  • CV cost variance
  • SV schedule variance
  • CPI cost performance index
  • SPI schedule performance index
  • TV time variable
  • FS finish-to-start
  • SS start-to-start
  • FF finish-to-finish
  • SF start-to-finish
  • ROM rough order of magnitude
  • DOM definitive order of magnitude
  • COQ cost of quality
  • DOE design of experiments
  • RCA root cause analysis

All None

Shared exercise

https://spellic.com/eng/exercise/capm-forkortningar.10981593.html

Share